July 1981 PA was signed by Japex Oman |
|
1981-1983 2D Seismic Acquisition |
|
1983 Aug spudded the 1st well |
|
1986 Drilled 12 exploration and appraisal
wells |
|
1987-Long term flow test of Daleel-1 & 2 |
|
1989-1990 Drilled Daleel-8 and declared
commercial discovery and commenced the 1st
development phase of drilling 20 wells,
Early Development Facilities and 8 inch
crude export pipeline |
|
1990 Jul Commenced the first commercial
production from Daleel via |
|
1994-1997 2nd development phase :3D Seismic
acquisition and 18 wells mostly horizontal |
|
1997-1999 3rd development phase: 3D Seismic
acquisition and 5 wells mostly horizontal |
|
2001-2002Jul No Further Activity Phase:
Tender & Take over Processes, production
declined to 4,100 bpd |
|
2002 Jul 24th Take over of the asset
operations by Daleel Petroleum |
|
2002 Nov Started water injection in one
of the oil producers |
|
2002 Dec Production increased to 7,000 bpd
by brining production from satellite fields
( Mezoon & Bushra) |
|
2003 Feb Spudded 1st well after the take
over by Rig-1 |
|
2003 Oct Spudded Rig-2 |
|
2003 Oct Obtained 3D Seismic Acquisition |
|
2005 Jun Oil processing capacity to 25,000
bpd by de-bottlenecking the existing
Production Facilities |
|
2005 Jul Commissioned the facilities for
supplying source water to Daleel ( 70,000
bpd) |
|
2005 Aug Production reached 16,553 bpd, the
highest in Daleel field history |
|
2006 Feb Water Injection rate increased to
21,780 bpd ( in 6 injectors) |
|
2006 Mar Started 3 D seismic acquisition to
cover the whole of the concession area |
|
2007 Contracted a 3rd drilling rig in order
to implement the full filed implementation
of water flooding as per Daleel FDP |
|
2008 Commissioned the Water Treatment and
Injection Facilities . Commissioned the Gas
Plant Facility. Made a new oil discovery ,
Bushara, in the east area. of the concession |